Project reporting under Horizon 2020

This article provides a detailed overview of project reporting under the Horizon 2020 programme, explaining the differences and specifics of continuous, periodic, and final reports.

Reporting is an essential activity in Horizon 2020 financial management, as every project manager needs to not only maintain control and steer project progress but also inform the project sponsor about progression of the work towards its agreed objectives. When reporting on the project status, you will have to cover not only scientific and technical advances but also financial aspects like cost consumption and other activities related to commercialization, communication, and project management.

Why is project reporting important?

Project reporting is an essential part of any company’s project management best practices, as it allows a comparison of how the project is performing against the original planning, schedule, and budget. It assists in early detection of deviations and indicates if resources are being distributed efficiently. In my view, the most important benefit of good project reporting is to improve the decision-making process: an informed decision could potentially lead to a better outcome.

How to report in Horizon 2020?

In the past, there used to be a few ways to provide the EC with a summary progress report but lately the EC asks to upload a set of aggregated project reporting data online via the Funding & Tenders Portal.

In Horizon 2020 project reporting is divided into three categories or types of report, and each of these is rated slightly differently.

Continuous reporting

    As implied by its name, this type of project reporting in Horizon 2020 runs in a continuum from the beginning to the end of the project. Partners mainly provide information on the status of deliverables and milestones, but there are many other areas that you could inform the EC about: such as risks affecting the project, scientific papers published, advancement on intellectual property management, or project dissemination initiatives. Information provided during continuous project reporting is assessed at the time of each periodic report is submitted.

    Periodic Report

      As the name suggests, for the periodic report in Horizon 2020 you have to report on the progression of work done over a certain period of time, also known as the reporting period. The length of such periods can vary from 3 to 18 months and they are defined by the EC in the grant agreement (GA) at the beginning of the project.

      The Periodic Report is subdivided into technical and financial reports. While the technical report describes progression of scientific/technical work, the financial report covers project budget allocation and the financial statements.

      The Technical report itself consists of two parts, Part A (directly entered into forms onto the Funding & Tenders Portal) and Part B (uploaded as PDF to the Portal).

      • Part A covers identical areas to the continuous project reporting, i.e. if you have kept the continuous project reporting up to date and in a timely manner, then it is very likely that most of the job is done by the time of preparing the Periodic Report. There is a particular section in Part A called summary for publication where you are asked to provide an overview summary on progression of work done towards the expected impact of your project on the economy, society, and environment. Later, this section of Part A is going to be published on the EC’s Community Research and Development Information Service website (CORDIS) where it will become publicly accessible to anyone. The idea behind CORDIS is to centralize project achievements and outcomes and serve as source of networking and synergies among business and organizations.
      • Part B is a project status report and completely different from Part A, since it covers an extensive and fully detailed narrative of the progression of the work done, from project objectives, work packages, and tasks’ progress descriptions to the use of resources (human and financial). Most project managers request interim reports and continuously gather required information from partners, WP or task leaders during the project reporting period, in order to be on track and have everything ready for the Periodic Report. Also, any deviations from original planning should be explained here.

      The Financial Report refers to the consumption of the project costs incurred during the period. If you have implemented a regular interim cost reporting, then you will most likely only have to pull out the financial data covering the period for this report. This financial data is then summarized on a financial statement containing aggregated figures of the different costs categories such as personnel, subcontracting, travels, equipment, and other goods and services, and indirect costs. The financial statements are prepared and submitted online via the Funding & Tenders Portal. Every interim payment by the EC is subject to approval of the financial report and represents a percentage to be reimbursed on total cost accepted by EC (some costs may be rejected during assessment due to not being eligible), normally 70% reimbursement rate for for-profit entities.

      In Horizon 2020, one Periodic Report is prepared and submitted per period. During periodic reporting no other documents, apart from the ones mentioned above, have to be provided to EC. Meaning that invoices, contracts, time-sheets, and other proof of payments must be kept on file, but are not required to be submitted unless explicitly asked for. The EC may even order an audit up to 2 years after the final payment.

      Final report

        This is similar to periodic reporting, in the sense that it includes both technical and financial aspects, where the tech part is also divided into A and B and a financial statement needs to be submitted. The main difference to a periodic report is that the final statement must be certified. This is also known as certification on financial statements or CFS. An independent auditor certifies that costs of the financial statements are eligible. In case of financial errors committed in previous periods, the final report would provide an opportunity to correct them.

        In summary, project reporting represents a fair amount of administrative work, however it is mandatory under the Horizon Europe programme. The more detailed and clear the information is prepared, the fewer clarifications will be asked, which reflect in faster interim payments.

        Also, good to know: project reporting documentation is reviewed by EC (project office, financial officer, potentially an ethics committee) and a pool of external independent experts in the project field. From project reporting submission date, EC has up to 90 days to review and pay.

        This article is written by Juan Jose Vazquez, Project Manager EU programmes Horizon Europe & Horizon 2020.

        Recorded webinar: Preparing your periodic reports under H2020

        Watch this recorded webinar focused on the questions of how to prepare periodic reports under Horizon 2020 and how to master the administrative and financial management rules of H2020.

        Budget, design, and manage Horizon Europe projects together

        Empower your teams to work together on project schedules and budgets, all while writing proposals and managing projects. Start with our 30-day free trial today! Once the trial is over, you can continue by using our free plan with unlimited users and essential functionalities or switch to one of our paid plan options.

        Subscribe to our Newsletter to get updates and expert insights straight to your mailbox.

        STAY INFORMED

        Updates and expert insights straight to your mailbox